CORPORATE PLAN KEY ACTION PLAN 2017/18 - QUARTER 2 PROGRESS

Meeting: 05/12/2017 - Governance Select Committee (Item 34)

34 CORPORATE PLAN KEY ACTION PLAN 2017/18 - QUARTER 2 PROGRESS pdf icon PDF 135 KB

(Director of Governance) To consider the attached report.

Additional documents:

Minutes:

The Select Committee received a report regarding the Corporate Plan Key Action Plan 2016/17 – Quarter 2 from the Assistant Director, Governance.

 

The Corporate Plan was the Council’s key strategic planning document, setting out its priorities over the five year period from 2015/16 to 2019/20. The priorities or Corporate Aims were supported by Key Objectives which provided a clear statement of the Council’s overall intentions for these five years.

 

The Key Objectives were delivered by an annual action plan with each year building upon the progress against the achievement of the Key Objectives for previous years. The annual action plans contained a range of actions designed to achieve specific outcomes and were working documents and therefore subject to change and development to ensure the actions remained relevant and appropriate and to identify opportunities to secure further progress or improvement.

 

The Corporate Plan Key Action Plan for 2017/18 was adopted by Council at its meeting on 27 September 2016. Progress in relation to all actions and deliverables was reviewed by the Cabinet, the Overview and Scrutiny Committee and the appropriate Select Committee on a quarterly basis.

 

There were 50 actions in total for which progress updates for Quarter 2 were as follows:

 

(a)             42 (84%) of these actions had been Achieved or were On Target;

(b)             2 (4%) of these actions were Under Control;

(c)             6 (12%) were Behind Schedule; and

(d)             0 (0%) were Pending.

 

There were 8 actions that fell within the areas of responsibility of the Governance Select Committee. At the end of Quarter 2 these were:

 

(a)             8 (100%) of these actions had been Achieved or were On Target;

(b)             0 (0%) of these actions were Under Control;

(c)             0 (0%) of these actions were Behind Schedule; and

(d)             0 (0%) of these actions were Pending.

 

RESOLVED:

 

That the Corporate Plan Key Action Plan 2017/18 Quarter 2 Progress Report be noted.